This doc owns the developer-held exemption-certificate pathway: the route by which a foreign buyer of a new (or near-new) dwelling does not lodge an individual foreign-investment application because the developer holds a certificate covering the sale. It grounds the firb_workflow "do I even need to apply?" branch (component 4) — the simplest, fastest path, common for off-the-plan apartments. It does not own the individual application (Applying for FIRB approval — the process), the fee (FIRB application fees — the current dollar schedule), or the eligible-types taxonomy (What property types a foreign person may buy — the positive taxonomy).

What it is

A property developer (Australian or foreign) can apply for a New Dwelling Exemption Certificate (or a Near-New Dwelling Exemption Certificate) to sell new/near-new dwellings in a specified development to foreign persons. Where the developer holds the certificate, the individual foreign buyer is not required to seek their own foreign-investment approval to buy a dwelling in that development.

The buyer-side limit — the $3M cap

The certificate exempts a foreign person from individually seeking approval to buy new dwellings up to a cumulative total of $3 million in the specified development. Above $3 million cumulative, the certificate does not cover the purchase and the foreign person must apply for their own foreign-investment approval (Applying for FIRB approval — the process). This is the single most load-bearing fact for the plan: the developer certificate is a clean path only under $3M cumulative; cross that line and the individual application (and its fee) re-enters.

The developer-side conditions (context, not the buyer's obligation)

These bind the developer, not the buyer, but shape whether the path is available:

For the buyer, the practical check is: ask the developer/agent whether a New Dwelling Exemption Certificate covers the dwelling — if yes and the price is under the $3M cumulative cap, no individual FIRB application is needed (only confirmation and a copy of the certificate).